top of page

Upper Piluwa 3 Small Hydropower Project (4.95 MW)

Client : Mabilung Energy Pvt. Ltd.

Service rendered : feasibility study update, detailed engineering design of civil and Hydro-mechanical equipments and preparation of technical specification of Electro-mechanical equipment.

Project Status : Study phase

 

The scheme is located in Sankhuwasabka district on Piluwa Khola. The scheme utilizes design discharge of 5.02 m3/s and topographical head of 121.1 m

Phalakhu Khola Hydroelectric Project (13.7 MW)

Client : Betrawati Hydro Electric Company Ltd.

Service rendered : detailed reveiw of feasibility study, detailed engineering design of civil and Hydro-mechanical equipments, preparation of Electro-mechanical specifications

Project Status : Study phase

 

The scheme is located in Rasuwa district on Phalkahu Khola. The scheme utilizes design discharge of 3.02 m3/s and topographical head of 588 m

 

Upper Mailung A Hydroelectric Project (6.42 MW)

Client : Energy Engineering Pvt. Ltd.

Service rendered : detailed reveiw of feasibility study, topographical survey of transmission line and detailed engineering design of civil works

Project status : Under construction

 

The scheme is located in Nuwakot and Rasuwa districts on Mailung Khola. The scheme utilizes design discharge of 1.746 m3/s and topographical head of 452.5 m.